How to prepare your roof, stud wall and floor for blown-in insulation
You do the preparation, we blow in the insulation. This guide tells you step by step what to do. In doubt? Call us, it saves you work later.
Allow 5 to 10 half-days for an average roof, stud wall or floor.
A bit of Reinder Douwes and a bit of AI
You take care of
Inspection for moisture and leaks
Levelling purlins or studs
Fit the appropriate reinforced membrane (required)
Sealing the membrane with tape and sealant
Fitting battens
Preparing the wiring
Clearing the space for blowing
We take care of
Blowing in insulation under pressure
Checking density and fill
Sealing the blowing holes airtight again
Required: reinforced membrane, without staples
Only reinforced membranes are permitted for our blown-in insulation work. On the warm side (the interior side of the building), use a reinforced smart vapour membrane such as pro clima INTELLO PLUS. Note PLUS: this is the reinforced version, not standard INTELLO. On the cold side, use a reinforced vapour-open membrane such as pro clima MENTO PLUS. For example, when insulating a ground floor from below, the membrane beneath the floor joists sits on the cold side of the insulation, facing the crawl space. Use a vapour-open membrane there, not a smart vapour membrane. Reinforcement strengthens the membrane against the pressure during blowing. Do not use staples: they can tear out and cause holes. Fix the membrane temporarily with double-sided tape, then screw the battens on straight away.
At what density do we blow in?
Material
Density
Conductivity (W/(m K))
Cellulose
45 - 55 kg/m³
0.038
Wood fibre
35 - 45 kg/m³
0.038
Cardboard
35 - 45 kg/m³
0.038
Straw
90 - 110 kg/m³
0.044
Straw is heavier. For straw, use rafters and battens one size heavier than the table in step 2.
1. How does the system work?
First fit the appropriate reinforced membrane and the battens: a smart vapour membrane on the warm side, a vapour-open membrane on the cold side. We then blow in the insulation. Fit the plasterboard only after blowing.
On the warm side of the insulation, facing the interior. PLUS is the reinforced version. The smart membrane regulates vapour transport and allows drying back inwards.
On the cold side of the insulation, for example beneath ground-floor joists facing the crawl space. Vapour-open and windtight; not a smart vapour membrane.
Battens
You, before blowing
Hold the membrane in place during blowing and support the insulation. Must be fully fitted before blowing.
Blown-in insulation
Us
Fills every gap, no thermal bridges, good sound damping.
Plasterboard
You, after blowing
Forms the finish on the battens. Fit only after blowing.
A single 1 mm gap lets up to 800 grams of moisture per metre of joint into the construction each day. That is 1600 times more than through a properly fitted membrane. Airtightness is not a detail.
Airtight layer on the warm side, vapour-open on the outsideA leak in the membrane: warm, moist air flows into the insulationA 1 mm gap lets through a lot of moisture, so every seam mattersSmart membrane on the warm side: protection in winter, drying out in summerWith a smart membrane on the warm side, moisture can dry back inwards in summer
On the warm side of the insulation, facing the interior. PLUS is the reinforced version. The smart membrane regulates vapour transport and allows drying back inwards.
On the cold side of the insulation, for example beneath ground-floor joists facing the crawl space. Vapour-open and windtight; not a smart vapour membrane.
Double-sided tape (e.g. Duplex)
Along every rafter
Temporary fixing, instead of staples
Tescon Vana tape 60 mm
1 roll per 30 m²
Overlaps and joints on timber
Orcon F sealant
2 tubes per 30 m²
Joints on brick, concrete and plaster
Tescon Profect / Contega SL
Per window
Window corners and gaps at frames
Roflex / Kaflex grommets
Per penetration
Cables and pipes through the membrane
Rafters or studs C24
See table
Supporting structure
Battens according to purlin span table (C18)
300 mm centres
Hold membrane and insulation, base for plasterboard
Screws 35-40 mm
Per crossing
Fixing battens
Rd (m² K/W)
Cellulose / wood fibre / cardboard thickness
Straw thickness
3.5
133 mm
154 mm
4.0
152 mm
176 mm
5.0
190 mm
220 mm
6.0
228 mm
264 mm
Purlin span
Insulation thickness
Rafter
Centres
1.05 m
up to 200 mm
21 x 58 mm
300 mm
1.05 m
from 200 mm
28 x 58 mm
300 mm
1.50 m
up to 200 mm
28 x 70 mm (or 28 x 58)
300 mm (or 200)
Wall insulation thickness
Stud
Note
80 - 100 mm
44 x 69 mm
Anchoring to wall required
100 - 140 mm
38 x 100-120 mm (SLS)
Most common
140 - 220 mm
38 x 140-195 mm
Heavy construction
Indicative values at a conductivity of 0.038 W/(m K) for cellulose, wood fibre and cardboard, and 0.044 W/(m K) for straw. Rd = thickness in metres / conductivity. Rd is the resistance of the insulation material, not the Rc of the whole construction. Always check the declared conductivity and Rd of the selected product. Tools: screwdriver, sealant gun, cutter, tape measure, level with a metal straightedge over 2 m and a pressure roller. Span of 1.50 m? Call us first, structural advice is needed.
3. Inspection before anything else
Purlins and rafters are sound and load-bearing.
No moisture, mould or active leaks.
Check for a vapour-open windproof layer outside. If there is none, the inner membrane is even more important.
Gaps larger than 5 mm are sealed beforehand.
Timber moisture below 20% (use a moisture meter).
Walls: at least one brick thick (approx. 21 cm), no rising damp. Remove cement render and synthetic finishes.
Flue: enclosure of non-combustible material filled with stone wool, keep the manufacturer's clearance. Cellulose withstands up to 70 °C.
Cavity size: at least 9 cm width and depth between rafters, studs or joists, otherwise we cannot blow in properly.
Timber ground floor: beneath the joists, on the cold side facing the crawl space, fit reinforced vapour-open membrane such as pro clima MENTO PLUS with battens. Do not use a smart vapour membrane there.
Crawl space: at least 50 cm from the underside of the floor joists to the ground, so we can blow in and move around properly.
Moisture problem? Stop. Fix the cause first and let it dry to below 20% timber moisture.
4. Levelling
All purlins or studs must lie in one plane. An uneven plane causes bulges, gaps and a crooked finish later.
1Pick the most protruding purlin as reference.
2Lay the metal straightedge across the purlins and find the low spots.
3Pack low purlins with a batten until the straightedge touches everywhere.
4Maximum deviation 3 mm. Packing more than 50 mm? Call us first.
5Walls: plates on floor and ceiling, hammer plugs at 500 mm, studs at 600 mm, 10 mm clear of the wall.
5. Fitting the reinforced membrane, without staples
Use only reinforced membranes. On the warm side, use a smart vapour membrane such as pro clima INTELLO PLUS. Note PLUS: this is the reinforced version. On the cold side, for example beneath ground-floor joists facing the crawl space, use a reinforced vapour-open membrane such as pro clima MENTO PLUS, not a smart vapour membrane. Follow the selected membrane's installation instructions for orientation and connections.
1Measure the length and add 40 mm at both edges for the connection.
2Apply double-sided tape to the rafters or studs.
3Press the membrane taut onto the tape, no creases or sagging. Do not staple.
4Next strip with 100 mm overlap, use the printed lines.
5Screw the battens onto the membrane as soon as possible (step 7). They hold it during blowing.
6Wrap window reveals fully and tape them to the frame.
The membrane says stapling is allowed. For blown-in insulation we advise against it: blowing pressure tears staples out and creates holes in the airtight layer. Already stapled? Cover every staple with Tescon Vana.
Membrane with the battens screwed on straight away
6. Sealing joints, edges and corners
The most important step: around 80% of air leaks are here. Take your time.
Overlaps: Tescon Vana centred on the overlap, crease-free, rubbed down firmly with the roller.
Brick, concrete or plaster: dust-free surface, a 10-15 mm bead of Orcon F, press the membrane in within 10 minutes with a small loop.
Timber: tape half on timber and half on membrane, or Orcon F on uneven timber.
Corners: Tescon Profect, stick one leg first, then the second.
Floor to wall junction: lay a waiting strip of membrane, so no draught enters the insulation via the floor joint.
Tape sticks poorly below 5 °C or on dust and moisture.
Taping the membrane overlapPress the tape firmly with the applicatorSmooth the tape, no creasesApplying sealant at the wall junctionSealant bead on the timber for the junctionPressing the membrane into the sealant at the junctionNeatly taping corners and junctionsSealing penetrations with a grommet
7. Fitting battens (before blowing)
Battens according to the purlin span table in step 2 (21 x 58 mm, 28 x 58 mm or 28 x 70 mm), at least C18, perpendicular to purlins or studs.
300 mm centres (max. 500 mm).
Screw at every crossing, screws at least 35 mm.
This creates approx. 20 mm service space for wiring.
Battens along the edges do not replace sealant and tape. Seal first, then fit battens.
8. Preparing the wiring
Make a wiring plan first to avoid holes.
Cables in the 20 mm space between battens, clips on the batten and never on the membrane.
Water and heating pipes do not belong in the service space.
Back boxes on the batten or on blocks, flush with the finish.
Every penetration with a Roflex grommet, never just cut a hole. Bundle cables.
No recessed spotlights: choose surface spots or LED panels.
9. Ready for our visit
Rooms empty and easy to reach.
2 x 230 V on different circuits (16 A).
We make the blowing holes (approx. 1 per 3-4 m²) and tape them crosswise and square afterwards.
On walls the holes are in the top third and we check extra near the floor.
The membrane may bulge slightly, but not stretch excessively.
For interior roof and stud-wall insulation, start with the plasterboard within 48 hours of blowing. Do not use OSB, plywood or underlayment: they block the membrane. Plasterboard or vapour-open wood fibre board is fine.
10. Quality and common mistakes
Mistake
Solution
Membrane stapled
No staples when blowing. Double-sided tape and battens straight away.
Membrane not taut
Pull tighter, battens at 300 mm.
Overlap poorly taped
Rub down fully with the roller.
Edges poorly sealed
Enough sealant, take your time.
Penetration not sealed
Always grommet, tape or sealant.
OSB or plywood as finish
Vapour-open boards only.
Poor levelling
Metal straightedge, max. 3 mm deviation.
Small tear in membrane
Up to 10 mm: Tescon Vana 50 mm over it. Larger: sealant plus tape.
Test yourself with a smoke pencil under low pressure: if smoke is drawn in, there is a leak. A blower door test gives a hard measurement.
Frequently asked questions
Unsure about something?
Call or message us. Better to check now than have a problem later.
We use functional cookies to make the website work properly and analytical cookies to understand our traffic. We place no tracking or advertising cookies.